Part of Radnor Township's mission is to make sure our residents are receiving the best quality services for your investment. A major way we accomplish this is through Township projects that benefit the whole community. Below you will find information regarding projects currently underway. (Please note this is an everchanging project list that will be updated frequently based on project status.)
Public Streets Affected by Utility Work in Radnor Township | |||
Date/Duration | Street(s) | Utility | Description of work |
Underway/September 2024 |
Conestoga Road (Sproul-County Line)
|
Aqua | Underground Water Main Replacement |
Underway/June 2024 |
Brooklea Road, Fairfax Road | Aqua | Underground Water Main Replacement |
Underway/April 2024 |
Governor Circle, Westover Road | PECO | Underground Electric Line Replacement |
Underway/July 2024 |
County Line Road | PECO | Underground Electric Line Replacement |
Underway/April 2024 |
Briarwood Road, Amherst Circle | PECO | Underground Electric Line Replacement |
Underway/May 2024 |
Chamounix Road | Radnor Township | Chamounix Road Culvert Replacement |
Underway/May 2024 |
South Devon Avenue, West Wayne Avenue | Radnor Township | Storm Sewer Installation |
Underway/June 2024 |
Malin Road, Briarwood Road | Aqua | Underground Water Main Replacement |
February/August 2024 |
Eagle Road, Amherst Circle, Overhill Road | PECO | Underground Gas Main Replacement |
February/April 2024 |
Arden Road | PECO | Overhead Utility Line Replacement |
February/March 2024 | King of Prussia Road, between Lancaster & Radnor Chester Road | PECO | Underground Electric Lines |
February/June 2024 |
Inverary Road, Darby Paoli Road | PECO | Underground Electric Line Replacement |
2024 (start date TBD) |
Briarwood Road, Amherst Circle, Lawrence Road | Aqua | Underground Water Main Replacement |
2024 (start date TBD) |
Knox & Watch Hill Roads, Matlack and Hothorpe Lns. | Aqua | Underground Water Main Replacement |
2024 (start date TBD) |
Chamounix Road | PECO | Underground Gas Main Replacement |
2024 (start date TBD) |
Mill Road, Tower Road | PECO | Underground Gas Main Replacement |
2024 (start date TBD) |
Sunnyhill Road, Spring Mill Road | PECO | Underground Gas Main Replacement |
2024 (start date TBD) |
Eaton Road | PECO | Underground Electric Line Replacement |
2024 (start date TBD) |
Malin Road, Bryn Mawr Avenue | PECO | Underground Electric Line Replacement |
2024 (start date TBD) |
Landover Road | Aqua | Underground Water Main Replacement |
2024 (start date TBD) |
Haymarket Lane, Drakes Drum Drive | PECO | Underground Electric Line Replacement |
Note: Start dates and project durations are weather dependent. |